Bitcoin miner MARA prices $185 million in new debt for Ohio power plant buyout

Nov 20, 2026 08:08 Written by Newisty Editorial Team bitcoin mara mining debt ai
Bitcoin miner MARA prices $185 million in new debt for Ohio power plant buyout

Bitcoin miner MARA Holdings has priced $185 million in new debt at an 8.75% interest rate to help pay for its roughly $1.5 billion purchase of Long Ridge Energy & Power, a deal that includes a natural-gas power plant in Ohio. The company disclosed the bond pricing late Tuesday in a filing with the U.S. Securities and Exchange Commission (SEC), the agency that reviews public company disclosures.

The move comes about a week after MARA revealed it had sold $1.1 billion worth of bitcoin to repay loans that were secured against its bitcoin holdings. Those earlier loans had helped fund the Long Ridge acquisition. The new borrowing, by contrast, is tied to the power business itself.

Key numbers at a glance

  • $185 million in new debt, priced at an 8.75% interest rate.
  • Roughly $1.5 billion total cost for the Long Ridge acquisition, including existing debt.
  • $1.1 billion in bitcoin sold, with $750 million of the proceeds used to repay bitcoin-backed loans.
  • 13,597 BTC sold at an average price of about $81,039 after September.
  • The deal is expected to close on Nov. 27.

What the SEC filings show

MARA's subsidiary priced the new bonds to help finance the acquisition of Long Ridge Energy & Power. Long Ridge already has $600 million in notes carrying a similar 8.75% rate. Once the new borrowing is completed, annual interest payments on the combined $785 million would reach approximately $68.7 million, according to a CoinDesk calculation, including about $16.2 million a year on the new debt alone.

Financial statements filed Monday show Long Ridge generated $178.5 million in revenue during the first nine months of 2026 but recorded a $3.5 million net loss. MARA previously estimated its annualized adjusted earnings at $144 million, based on the second half of 2025.

What MARA is buying

Long Ridge operates a 485-megawatt natural-gas power plant in Hannibal, Ohio, along with more than 1,600 acres of land. MARA plans to develop that land into a computing campus for artificial intelligence customers.

MARA has reported interest from prospective large-scale customers and is targeting two data-center leases before the end of the year. The company has also warned that negotiations could stretch into 2027.

Stock reaction and market pressure

MARA shares rose about 4.7% to $6.72 in early Wednesday premarket trading, recovering part of Tuesday's 3.3% decline to $6.42. The stock is still down roughly 12.5% since Nov. 10, as falling bitcoin prices and the company's expansion into AI infrastructure weigh on its outlook.

A shift away from holding bitcoin

The financing marks a sharp change in how MARA funds its business. The company previously borrowed against its bitcoin reserves to help pay for the Long Ridge deal. It has now sold a large portion of those holdings and shifted the borrowing to the power business it is acquiring. MARA has also said it plans to sell more bitcoin, according to a earlier CoinDesk report cited in the article.

Why this matters

MARA, one of the larger publicly traded bitcoin miners, is using its power assets to build a business serving artificial intelligence customers. The company's move from bitcoin-backed borrowing to debt tied to a power plant shows how its funding strategy is changing as it expands beyond mining. Falling bitcoin prices have also pressured the company's shares in recent weeks.

What happens next

The Long Ridge acquisition is expected to close on Nov. 27. MARA is also aiming to sign two data-center leases before year-end, though it has cautioned that talks could extend into 2027.

Sources

Newisty Editorial Team
Written by

Newisty Editorial Team

Technology · Crypto · Digital Economy
View all posts

Newisty Editorial Team covers technology, cryptocurrency, digital products, online platforms, developer tools and the wider digital economy. Our content is researched from official sources, company announcements, public documentation, market data and other primary or reputable sources. Articles are reviewed and edited before publication for clarity, accuracy and useful context.

Comments (0)

Leave a comment
Your comment will appear publicly after submission.
No comments yet. Be the first to comment!