US data center construction fell 28% in Q3, its first drop in over a year
US data center building slows for the first time in over a year
Construction of new data centers in the United States fell 28% in the third quarter of 2026. It was the first quarterly decline in more than a year, according to data from research firm Cleanview.
Developers started building facilities with 8.4 gigawatts of power capacity between July and September. That is down from a record 11.7 gigawatts in the previous quarter. The slowdown raises questions about the future of an AI infrastructure buildout that Cleanview estimates will cost about $1 trillion for projects started this year.
Key numbers from the report
- Third-quarter construction starts fell 28%, the first quarterly drop in more than a year.
- Developers began 8.4 gigawatts of capacity, down from a record 11.7 gigawatts in the prior quarter.
- The number of buildings starting construction fell to 65 from 96.
- The quarter still ranked third-highest in Cleanview's records and was up 55% from the same period last year.
- Cleanview founder Michael Thomas estimated data centers that began construction this year will cost about $1 trillion to build and equip.
How Cleanview tracks the data
Cleanview's findings come from an analysis of thousands of satellite images covering more than 1,300 data center buildings across the US. The firm marks a construction start when visible vertical work appears, such as steel, walls, or columns going up. Grading work, a bare slab, or a company announcement alone do not count.
October brought a sharp rebound
Construction picked up again in October. Developers started facilities representing 4.6 gigawatts of capacity, the second-highest monthly total in Cleanview's records and nearly double the amount that began construction in October 2025.
Three large projects made up about 35% of the month's activity:
- 720 megawatts at Nscale's Monarch campus in West Virginia.
- 461 megawatts at Related Digital's Stargate Michigan campus.
- 450 megawatts at Crusoe's Abilene campus in Texas.
Together, these projects represent roughly 1.63 gigawatts of new construction.
Is the slowdown lasting?
Michael Thomas, founder of Cleanview Energy, said it is too early to conclude that the third-quarter decline signals a lasting slowdown. He noted that a lasting slowdown would affect utilities planning new power plants, companies making chips and turbines, and a stock market that has bet heavily on AI.
If October's pace continues through November and December, fourth-quarter construction starts could reach a record 14 gigawatts. That figure is a projection based on the current pace, not a confirmed outcome.
Why it matters
Data center expansion has become central to the global AI investment boom. A slowdown in construction affects companies that supply chips and turbines, utilities that plan new power plants, and investors with large positions in AI-related stocks. The third-quarter drop and the October rebound point in different directions, so the trend remains uncertain.